29 March 2011
- Erection works for Power Supply System for Kabul International Airport of Islamic Republic of Afganistan (Ministry of Transport).
- Laying of 66KV Cables (31.8 KMS) from Rajghat to New Delhi RSS of DMRC SYS-2.
- Laying of 33KV Cables (24.6 KMS) and 25KV Cables (13.8 KMS) in tunnel from Viswa Vidyalaya to Central Secretariat for DMRC SYS-2
- Installing of 22/.415 KV Auxiliary Sub-Stations (11 nos.) between Vishwa Vidyalaya and Central Secretariat Section of DMRC SYS2.
- Installing of 33KV Cables (11.4 KMS) and Installing of 33/.415 KV Auxiliary Sub-Stations (2 nos.) on viaduct between Trinagar and Rithala of DMRC RC-7B.